Time between roof going on and build being finished

We’ve got the roof on now and just trying to get a rough idea how much longer the build will take?

Asked by Adam on 16th Aug 2025
Expert Trade Answers
"Normally around the 7 day mark because it's all the preparation the the time putting the tiles or slates on"
Answered on 18th Aug 2025 - Member since Jan 2025 - report
"Depending on material ie slate or tile a standers semi detached house
Abound 4 to 7 days
Fully complete scaffold down"
Answered on 24th Aug 2025 - Member since Jun 2025 - report
"From start to finish depending on the size of a house i normally say a 5 to 6 days turn around, it is obviously weather dependent to."
Answered on 18th Aug 2025 - Member since Mar 2019 - report
"It deepens how good your tradesmen are , I am a skilled roofer so 3 days to complete your roof ,electricians 4 days ,plastering 5 days but i am talking about first class trades men thanks"
Answered on 28th Aug 2025 - Member since Mar 2025 - report
Find Tradespeople, compare up to 3 quotes!
It's FREE and there are no obligations
Ask a Trade
Got a question that only a tradesperson can answer? We have thousands of trades ready to answer any question you may have.
Ask your question
Ask a Trade

Are you looking for advice on a DIY project or have a question for our tradespeople?

We'll email your question to tradespeople who are skilled in your chosen category.

Your question will be made public - please do not include any personal details.

{{ first(ask.errors)[0] }}

By continuing you agree to the Community Guidelines.

Report Content

{{ first(reportForm.errors) }}

Thank you

Your report has been created and will be investigated shortly.

Ready to get a price for your home improvement project?
Get started

Over 1 million homeowners and over 50,000 tradespeople
use MyJobQuote nationwide each year