Ask your QuestionWhen fitting a shower tray, toilet and sink do l tile the walls before or after?
Asked by Deborah on 11th May 2021Best Answer
"Shower tray needs to be installed before tiling. If you’re tiling half/all walls then all tiling should be completed before install of basin/toilet. If you’re just having a splash back on the sink then the tiling for that would be done after sink installation."
Answered on 11th May 2021 - Member since Mar 2021 - report"100%tile first then grout all tiles then you can fit shower tray toilet and basin"
Answered on 11th May 2021 - Member since Jun 2019 - report"I would fit shower tray first then tile all walls before fitting toilet and hand basin."
Answered on 11th May 2021 - Member since Feb 2020 - report"Must be tile first walls and floor and after the furniture goes in
If not isn’t going to be right way done"
"Fit your shower tray first then Tile before fitting toilet and basin."
Answered on 22nd Jun 2021 - Member since Dec 2019 - report"Only shower trays/baths need to be installed before tilting.
Hope this helps"
"Fit the shower tray then tile all the walls and floor then fit the bathroom suite"
Answered on 3rd Jun 2021 - Member since May 2021 - report"Its like parenting there is no real right or wrong answer aslong as the work is done correctly obviously when i Aqua board a wall i do this first or larger tiles gives a nice flat surface to key the tray to but the prep is the key to a good install"
Answered on 11th May 2021 - Member since May 2021 - report"Tile wall after you have fitted shower tray then fit tiles then fit toilet and sink"
Answered on 19th May 2021 - Member since Apr 2021 - report